Initial draft of project plan
2010-11-12
Email from Nick
Chris and I spent some time today trying to clarify the technical tasks we need to accomplish between now and next March. The attached file is a planner document, which identifies the tasks, and our respective time allocations to them. It is an early draft, which is just as well, since Jeff and I appear to be about 120% committed for all of December and January.
Can you identify tasks I have missed, or any resource allocations you think are wrong? Once we've got a definite set of tasks and allocations, we will be able to discuss with Tim whether to reschedule some of the work, or bring in additional resources.
Number of VMs Available
I've not really started to go through the document in detail. But it dawned upon me that if we have a target of test deployment of i2b2 on the UHLT side by February, then we are currently severely constrained by the lack of test VM's. Jeff.
Infrastructure – Development Environments
My understanding is that this would cover:
- A project within svn for each.
- Built artifacts within a maven repository.
- Some explanatory documentation on the wiki and probably notes within the projects themselves.
- Install procedures held within svn.
What is not covered so far in the planner:
- Labels Webapp (has a project in svn),
- UIDGEN (has a project in svn)
- The ability to design label formats. Knowledge of the latter is restricted to Vasil working in a Windows environment. There is no project within svn covering this.