wiki:LEGACY - Integration phase 20101112

Version 7 (modified by jeff.lusted, 13 years ago) ( diff )

--

Initial draft of project plan

2010-11-12

Email from Nick

Chris and I spent some time today trying to clarify the technical tasks we need to accomplish between now and next March. The attached file is a planner document, which identifies the tasks, and our respective time allocations to them. It is an early draft, which is just as well, since Jeff and I appear to be about 120% committed for all of December and January.

Can you identify tasks I have missed, or any resource allocations you think are wrong? Once we've got a definite set of tasks and allocations, we will be able to discuss with Tim whether to reschedule some of the work, or bring in additional resources.

integration-phase-20101112


Number of VMs Available

I've not really started to go through the document in detail. But it dawned upon me that if we have a target of test deployment of i2b2 on the UHLT side by February, then we are currently severely constrained by the lack of test VM's. Jeff.

Attachments (1)

Download all attachments as: .zip

Note: See TracWiki for help on using the wiki.