| 1 | Early draft of project plan |
| 2 | |
| 3 | Email from Nick |
| 4 | |
| 5 | Chris and I spent some time today trying to clarify the technical tasks we need to accomplish between now and next March. |
| 6 | The attached file is a planner document, which identifies the tasks, and our respective time allocations to them. |
| 7 | It is an early draft, which is just as well, since Jeff and I appear to be about 120% committed for all of December and January. |
| 8 | |
| 9 | Can you identify tasks I have missed, or any resource allocations you think are wrong? |
| 10 | Once we've got a definite set of tasks and allocations, we will be able to discuss with Tim whether to reschedule some of the work, or bring in additional resources. |