Early draft of project plan Email from Nick Chris and I spent some time today trying to clarify the technical tasks we need to accomplish between now and next March. The attached file is a planner document, which identifies the tasks, and our respective time allocations to them. It is an early draft, which is just as well, since Jeff and I appear to be about 120% committed for all of December and January. Can you identify tasks I have missed, or any resource allocations you think are wrong? Once we've got a definite set of tasks and allocations, we will be able to discuss with Tim whether to reschedule some of the work, or bring in additional resources.